Bacton Gas Terminal
A new gas pipeline has been laid between Holland and the receiving terminal at Bacton in Norfolk
Southdowns was appointed to advise on the likely noise impact associated with the commissioning phases of the project, including the de-watering, drying, de-pressurisation (using silenced venting) and gassing of the pipeline. The activities were assessed in accordance with the site Code of Practice and consideration of other cumulative operations at the terminal.