Client Area

West Coast Route Modernisation - Contractor

Southdowns was appointed to provide expert noise and vibration advisory services to one of the main railway contractors reponsible for undertaking track renewals on the West Coast Route Modernisation project.

The project, which was part of a major rail upgrade scheme between London and Glasgow, required a 5 month blockade to complete the works. The length of the blockade required certain working to be undertaken outside of normal hours and hence there were concerns over the sensitivity of the works to nearby residents.

Southdowns was responsible for advising on three different route sections:

Section 2: Norton Bridge to Stoke
Section 11: Stafford to Colwich Junction
Section 12: Colwich Junction to Macclesfield

In total the renewals work took place through 5 different local authorities (Macclesfield, Congleton, City of Stoke, Newcastle Under Lyme and Stafford Councils), requiring careful co-ordination.

A programme of detailed baseline noise surveys was developed in conjunction with the Local Authorities. A total of 7 unattended (long-term) sites and 45 attended (short-term) monitoring sites were identified across the different sections of work in both rural and non-rural locations. In general the transient nature of the renewals works was of less concern than the continual use of depot sites on a 24 hr basis. As a result, the unattended monitoring was concentrated at properties close to these locations.

Southdowns was responsible for developing the draft Section 61 consent applications for all the works for the Contractor and liaising with the local authorities to address any comments. All calculation were undertaken using specifically designed systems to address the transient nature of the renewals works, along with other calculations to consider the set-up and continuous operation of the depot sites.

Working to a tight programme of submissions, Southdowns staff were able to gain consent for the Contractor and ensure that works commenced to programme, advising on mitigation measures in sensitive locations. These included the use of ‘exclusion zones’ for certain out of hours works and the installation of temporary acoustic screening around depot sites. Consent conditions were reviewed by Southdowns to ensure that risks to the Contractor were minimised.

Once the works had commenced, Southdowns were commissioned to undertake compliance monitoring both in terms of noise monitoring and also visual BPM and other Section 61 compliance issues. Monitoring was undertaken during specific early operations to verify the assumed sound power levels in the Section 61 calculations. In particular verification was required for the Track Renewals Train (TRT) and the Medium Output Ballast Cleaning (MOBC) trains. Results showed that the original assumptions were robust and hence no variations or dispensations were required.

Routine scheduled monitoring was also conducted across the route where works were known to be taking place. Unattended continuous monitoring stations which were set-up near to several depot sites were operated through the duration of the works and summary weekly reports were produced and submitted to the client to demonstrate compliance at the nearest properties.

In addition to the activities described above, Southdowns were also required to liaise with neighbouring contractors to ensure consistency in BPM discussions and overall calculated noise levels. Group meetings with all Contractors involved were held at intervals as well as co-ordination meetings with Network Rail.

Related services

Construction
Railways

Related projects

Croydon Tramlink Extension
Crossrail - Parliamentary Select Committee
Channel Tunnel Rail Link Contractors
West Coast Route Modernisation - Electrification Equipment
Southern Railway Train Operating Company
Thameslink Programme - CTRL Enabling Works
Southern Region Power Upgrade
Docklands Light Railway - City Airport Extension
A507 Baldock Bypass
Westminster City Council Rail Schemes Advice
Channel Tunnel Rail Link - Rail Link Engineering
Lewes Combined Sewer Outfall
Dublin Port Tunnel
DLR Woolwich-Arsenal Extension
Lincoln Station Re-modelling
DLR Langdon Park Station
St Pancras International Station
High Speed 1 - Tunnel Ventilation Shafts
Tottenham Court Road Station Upgrade
London Underground - Cooling the Tube Programme
East London Line Extension
Crossrail
Temporary Construction Railway - DLR Woolwich Ext.
Coal Bed Methane Drilling
Cambridge Junction, Hitchin
Queensland Road Development, London

Related news

Constructionline Pre-Qualification
Network Rail Framework
Crossrail Bill
Revised BS 5228 Published
DLR Woolwich Extension Unveiled
BSi Committee
Thames Tunnel Consultation
Railway Procurement Agency - Rep. of Ireland
Bond Street Station Upgrade

Related downloads

southdowns_general.pdf
southdowns_construction.pdf
southdowns_highspeed.pdf
southdowns_crossrail_contractors_Oct2010.pdf
southdowns_railways.pdf

© Southdowns Environmental Consultants Ltd

MAIN OFFICE
16 Station Street, Lewes,
East Sussex, BN7 2DB, UK

Tel: +44 (0)1273 488186
Fax: +44 (0)1273 488187

Reg No. 3150111

LONDON OFFICE

10 Greycoat Place, London
SW1 1SB, UK

Tel: +44 (0)207 9606255

Contact Us






website by BoxStuff